If you are sitting at a table with a few people and having a debate, and you see that the facts are against you and the longer the debate goes on, the worse things get for you, then don’t continue the debate; throw a dead cat onto the table, and everyone will forget the topic and talk about the cat.
Not because the cat solves the problem. But because, the moment it lands on the table, no one talks anymore about what was being discussed before; the cat takes everyone’s attention. This is called “strategic shifting of the public agenda,” while the example with the cat is called the “dead cat strategy,” which is mainly attributed to Australian political strategist Lynton Crosby, who urged the politicians he advised to create a political diversion when they saw they were losing the public debate.
Time and time again, the people of Kosovo have swallowed the dead cat served up by Albin Kurti’s Vetëvendosje, which specializes not in changing your mind about the real issue, but in shifting your focus from the real issue to dead cats.
What would happen, for example, if Vetëvendosje didn’t bombard us with such strategies? Perhaps we would talk about the Gjilan Highway. A project that began on April 15, 2018. From that date until today, exactly 8 years, 4 months and 16 days have passed. And the project has not been completed.
But hold on. We are not talking about an entire highway. We are talking only about a section of the highway, Banullë–Bresalc, and it is just 22.3 kilometers long. So, in nearly 9 years, not even 22 kilometers have been paved. That means not even two and a half kilometers have been paved per year. Meanwhile, more than 100 million euros have been allocated for this section, and not even 2 kilometers of road have been paved.
Back in 2023, a full 3 years ago, the government was lying that the section would be completed within that year.
“On the Pristina–Gjilan highway, specifically from Banullë to Bresalc, work is currently underway at a much faster pace. And we are optimistic that we will complete it by the end of the year,” said former Deputy Minister of Infrastructure Hysen Durmishi.
Albin Kurti himself was also lying.
“Pristina is being connected to Gjilan by highway. So, the Pristina–Gjilan Highway is being built,” Kurti said.
But someone might perhaps think that it is normal for 22 kilometers of highway not to be paved in nearly nine years. Let’s make a few comparisons.
The “Ibrahim Rugova” Highway began construction on April 25, 2010, and was completed on November 26, 2013. It is 77.4 kilometers long. So, it was completed in 3 years and 7 months.
Meanwhile, the “Arben Xhaferi” Highway, an extraordinarily complicated project, with long sections featuring bridges and tall concrete pillars whose foundations lie in a river, officially began construction on July 3, 2014, and all 65.5 kilometers were completed on May 29, 2019. 4 years and 10 months.
If we take both together, we have a total of 142.9 kilometers of highway paved in exactly 8 years and 5 months.
Let’s return once again to Gjilan. In 8 years, 4 months and 16 days, 22 kilometers of highway have not been paved.
Citizens should ask: Why was it possible to pave around 150 kilometers of highway in 8 years, but it is not possible to pave even 22 kilometers in another 8 years?
But this is a question the government does not want you to ask. This is a topic the government does not want you to discuss. This is a debate the government loses.
That is why it throws the dead cat onto the table, and unfortunately we are caught off guard once again by the same cat, the same strategy, and we all swallow it together.