The date is November 4, 2023.

Protective helmets on their heads, smiles in front of the cameras, a red ribbon ceremoniously cut (it starts with this sentence, but you don't see yourself, only the footage).

It was precisely here that Albin Kurti, Hekuran Murati, Liburn Aliu, Artane Rizvanolli and the chief executive of Infrakos, exactly 2 years ago, would inaugurate this tunnel and announce the reopening of the Hani i Elezit–Fushë Kosovë railway line.

Of course, it did not operate for a single day apart from that day, when the prime minister and his ministers would be photographed in a train carriage.

“We are giving it the attention it deserves, just as we are speeding up the train; we hope this project will speed up the Republic’s growth and development,” Albin Kurti declared.

Had the prime minister's ride that day lasted a little longer, we would have understood right from the start that it would take quite some time for the train to run on this railway.

The train was sped up and given attention only for the few hours set aside for this ceremony.

Media front pages were filled with the inauguration, which lasted only as long as the camera footage. 

It did not take long for the news of this reopening and the tunnels' becoming operational to appear on all the institutional websites.

Infrakos, yes.

The Ministry of Economy, yes.

And right up to the Office of the Prime Minister.

But from November 4, 2023, until today, not a single passenger train has run on this “reopened” line.

The media inauguration never became operational, because the railway line is not finished: no trains are running, the tunnels remain unfinished, and the bridges unrepaired.

Signalling and electrification are missing, while according to the information available to us, a tender for this work on the line has not even been opened yet.

Moreover, for this specific section and these inaugurated tunnels, the National Audit Office has also identified serious problems.

In the report published at the end of 2025, the auditor emphasizes that, “despite the importance of the project, its management by Infrakos, the Ministry of Infrastructure and the Ministry of Economy has failed to ensure efficient implementation.

According to the auditor, “poor communication between institutions, a lack of expertise and delayed decision-making have led to major delays and the overrun of the planned budget.”

But another finding is more telling.

The audit report shows that the tunnels inaugurated in November 2023 were still unfinished as of September 2024.

In fact, by that point, none of the seven tunnels on this section had been fully completed, just as they have not been completed even now.

In other words, they were inaugurated before being completed.